Wednesday, July 14, 2010

Our Kitchen Project – Day 13

Today was sort of an in-between day.  Our installation crew came in the morning to do a few odds and ends in the kitchen.  We went over some of the detail work remaining, to make sure we were all on the same page.  They installed the water line for the fridge, bringing it through the basement.  (Our basement ceiling is totally open, making it easy to run new electric, gas, and water lines – all of which we’ve had done - without drilling through walls.)  They also made a cutout in the peninsula for an outlet, which was the final piece we needed to prepare for tomorrow’s final electrician visit.  Our floor guys also came by to apply the second coat of polyurethane.   That means no walking on the floor for a while, which means you’ll have to wait until tomorrow for the latest pictures! 